Client: FDOT District 5
Lake County, FL

SR25a

Project Description:

E&R provided CEI services on two projects in this grouping which were constructed simultaneously. US 27 included milling & resurfacing of 6.9 miles, widening for auxiliary lanes and turnouts as well as drainage, driveway, guardrail and side road work. US 27 had 12 utilities on the project, all of which had a UWS for work during construction. SR 471 milling & resurfacing of 9 miles. MOT was a key component on both projects: SR 471 related to the one-lane, one-way operations and on US 27 related to business access and bike/pedestrian safety.

Services Provided:

Construction Management
Construction Engineering & Inspection

Performance Dates:

8/2017 to 12/2018

Construction Cost:

$13 million

 
 
 
 